A quick post....

The electrical inspection actually took place on Tuesday, and we passed the rough inspectiona nd have been cleared to close in the walls!!

So that is what we have been working on this week.

This is basically what we have to finish ( if I am understanding it correctly):
--put up the last of the sheet rock in all rooms
     --spackle/sand/repeat
     --paint in all rooms
--finalize the last coupel of drains
--put up wallboard in bathroom (around tub)
--put down bathroom floor
--put in tub and toilet
--paint in kitchen
--put down kitchen floor
--put in range, dishwasher, and refrigerator
--install overhead kitchen cabinets
--following painting of floor and ceilings, put down carpet in boys rooms
--install electrical covers on ALL outlets adn switches througout
--finish smoke detector set up installation
--put up molding
--get final electrical inspection
--get final CO inspection
--move in

so, yeah, a lot still to do, but in the final stretch.